LNER (SVR) Coach Fund
2006 Progress Page of Composite Coach GNR 2701

www.lner-svr-coachfund.org.uk



DECEMBER 2006


December with the family commitments that Christmas creates the pace has slowed this month on the larger tasks but has enabled some of the smaller jobs that have been put off have been finished like the last of the heater controls have been connected  and some for the netting has been fitted to the luggage racks. The one major task that has been completed is the fitting of the 3rd class corridor doors.

pro_2006_dec_4.jpg (59490 bytes)                     pro_2006_dec_3.jpg (59520 bytes)

pro_2006_dec_2.jpg (51346 bytes)                     pro_2006_dec_5.jpg (45441 bytes)


NOVEMBER 2006


November saw the second seat installed in compartment 2. Construction of the final 1st class seat back has been completed and is awaiting its turn to go to the upholster. At this rate the first class seating is on course to be finished around Christmas. Also for pictures in the view frames have been tried out.

pro_2006_nov_1.jpg (15339 bytes)                     pro_2006_nov_3.jpg (17820 bytes)

pro_2006_nov_4.jpg (16087 bytes)                     pro_2006_nov_5.jpg (14607 bytes)


OCTOBER 2006


October has been much the same more seat construction and the second seat installed in compartment 1 and one installed
in compartment 2.
Moving away from 2701 for a moment LNER 43600 was out shopped on 21st after 2 months of hard work by the staff of the Bewdley Paint shop and it is seen here at platform 2 Bewdley waiting to be put into the set, 52255 has now gone into
to the paint shop for the same treatment..
Also another shunt occurred 0n the 30th October using steam power giving a chance of getting interesting photographs.

pro_2006_oct_1.jpg (58616 bytes)                    pro_2006_oct_2.jpg (47736 bytes)

pro_2006_oct_3.jpg (47969 bytes)                    pro_2006_oct_4.jpg (43363 bytes)


SEPTEMBER 2006


September as with August has been spent on the first class seating the seat which was part covered as a trial has now been recovered with the real moquette and on the Friday of the Autumn Gala (22-9-2006) the arm rests and seat winds were assembled to the seat back and the installed, only 6 more to go plus the third class.

pro_2006_sep_1.jpg (47327 bytes)                 pro_2006_sep_2.jpg (50583 bytes)

pro_2006_sep_3.jpg (47419 bytes)


AUGUST 2006


August has been spent concentrating on the first class seating with the completion of the seat back frames fitting of
the springs through to the trial run with upholstery.

pro_2006_aug_1.jpg (21059 bytes)                 pro_2006_aug_2.jpg (18139 bytes)

pro_2006_aug_3.jpg (19451 bytes)                 pro_2006_aug_4.jpg (14605 bytes)

pro_2006_aug_5.jpg (33615 bytes)


JULY 2006


Start of the completion of the end of the third class corridor

pro_2006_jul_3.jpg (35467 bytes)

pro_2006_jul_1.jpg (35467 bytes)                 pro_2006_jul_2.jpg (29558 bytes)


JUNE 2006


Here are a selection of photos showing the advanced state of the corridor and gangways

pro_2006_jun_8.jpg (27163 bytes)                  pro_2006_jun_7.jpg (21802 bytes)

 

pro_2006_jun_1.jpg (92624 bytes)                 pro_2006_jun_2.jpg (93267 bytes)

   

pro_2006_jun_5.jpg (78598 bytes)                  pro_2006_jun_6.jpg (76095 bytes)

pro_2006_jun_3.jpg (80230 bytes)                  pro_2006_jun_4.jpg (68094 bytes)


MAY 2006


On the 3rd May GNR 2701 along with Kitchen Restraint car 7960 were shunted out on to the running lines of Bewdley Station using the Rushton shunter for coupling trials and to identify any rattles or movement within the structure of the carriage

P1000303t.jpg (49608 bytes)                  pro_2006_may_3.jpg (50928 bytes)

 

pro_2006_may_2.jpg (61262 bytes)                  pro_2006_may_4.jpg (63016 bytes)

 